Question: 3 E. Using complexity weighting scheme (see table 5.2 p. 144) and fucntion point complexity weighted table below 4 Estimate the total function point count

3 E. Using complexity weighting scheme (see table 5.2 p. 144) and fucntion point complexity weighted table below 4 Estimate the total function point count 5 Assume historical data suggests 5 fucntion points equal one person and 6 people have been assigned to work on the proje Questions: (must show your work under each for points) 1) What is the estimated project duration? 2) If 20 people are avaialble for the project, what is the estimated project duration? 3) If 40 people are avaialble for the project, what is the estimated project duration