Question: 3) Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in

3) Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in

a. 13 days or more

b. 11 days or less

c. between 12 and 14 days

3) Find the critical path and the project

3) Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in a. 13 days or more b. 11 days or less C. between 12 and 14 days Activity A B C D E Immediate Optimistic Most Probable Pessimistic Predecessor Duration Duration 1 5 2 6 2 5 3 7 1 10 A, B A, B C, D Duration 3 4 4 5 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!