Question: 3) Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in

3) Find the critical path and the project

3) Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in 13 days or more 11 days or less between 12 and 14 days a. b. C. Activity Immediate Predecessor Optimistic Most Probable Duration Duration 1 3 Pessimistic Duration A 5 2 4 6 B 4 5 A, B A, B C, D 2 3 D 5 7 E 1 2 10