Question: Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in a
Find the critical path and the project completion time for the following list of activities. Calculate the
probabilities of completing the following project in
a days or less
b days or more
Activity
Immediate
Predecessor
Optimistic
Duration
Most Probable
Duration
Pessimistic
Duration
A
B
C A B
D A B
E C D Find the critical path and the project completion time for the following list of activities. Calculate the
probabilities of completing the following project in
a days or less
b days or more
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
