Question: Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in a

Find the critical path and the project completion time for the following list of activities. Calculate the
probabilities of completing the following project in
a)11 days or less
b)13 days or more
Activity
Immediate
Predecessor
Optimistic
Duration
Most Probable
Duration
Pessimistic
Duration
A -239
B -244
C A, B 246
D A, B 258
E C, D 1310Find the critical path and the project completion time for the following list of activities. Calculate the
probabilities of completing the following project in
a)11 days or less
b)13 days or more
 Find the critical path and the project completion time for the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!