Question: 3 Given the foblowing activity network- Activity At takes 5 weeks, A2 takes 8 weekk, and A3 takes 2 weeks. What is the earliest start

3
3 Given the foblowing activity network- Activity At takes 5 weeks, A2

Given the foblowing activity network- Activity At takes 5 weeks, A2 takes 8 weekk, and A3 takes 2 weeks. What is the earliest start the of A2? Mapie Chace 5 wewes 15 wekis 43 metu 15 weet