Question: Given the following activity network: Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 3 weeks. What is the earliest start time
Given the following activity network: Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 3 weeks. What is the earliest start time of A3? weeks