3. Given the following information for a process, the process flow time would be:

Activity

Flow Time

Preceding Task

A

10 min

None

B

6 min

A

C

12 min

A

D

8 min

B

E

4 min

C

F

5 min

D, E

  1. What is the critical path?
  2. How many minutes will this project take?
  3. If activity C is crashed by 3 minutes, how many minutes will the project take?