Question: 3. Given the following table, construct a network diagram, either AOA or AON. Times are in days. a. Determine the expected duration of the project.

3. Given the following table, construct a network

3. Given the following table, construct a network diagram, either AOA or AON. Times are in days. a. Determine the expected duration of the project. b. Compute the probability that the project will take at least 18 days. Path Activity Time Estimates Top A 4-5-6 B 7-8-10 3-5-9 Bottom D 7-8-11 E 2-3-4 F 1-4-6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!