Question: Given the following table, construct a network diagram, either AOA or AON. Times are in days. a. Determine the expected duration of the project. b.
.png)
a. Determine the expected duration of the project.
b. Compute the probability that the project will take at least 18days.
Path Activity Time Estimates 4-5-6 7-8-10 3-5-9 7-8-11 2-3-4 1-4-6 Top Bottom E
Step by Step Solution
3.34 Rating (163 Votes )
There are 3 Steps involved in it
Draw the network Path Activity Optimistic Most Likely Pessimistic Mean Standard Deviation ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
372-B-M-L-O-M (3497).docx
120 KBs Word File
