Question: Given the following table, construct a network diagram, either AOA or AON. Times are in days. a. Determine the expected duration of the project. b.

Given the following table, construct a network diagram, either AOA or AON. Times are in days.

Given the following table, construct a network diagram, either AOA

a. Determine the expected duration of the project.
b. Compute the probability that the project will take at least 18days.

Path Activity Time Estimates 4-5-6 7-8-10 3-5-9 7-8-11 2-3-4 1-4-6 Top Bottom E

Step by Step Solution

3.34 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Draw the network Path Activity Optimistic Most Likely Pessimistic Mean Standard Deviation ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

372-B-M-L-O-M (3497).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!