Question: The answer needs to be entered in Excel. Please provide formulas, where applicable. Given the following table, construct a network diagram, either AOA or AON.

The answer needs to be entered in Excel. Please provide formulas, where applicable.

Given the following table, construct a network diagram, either AOA or AON. Times are in days.

a.) Determine the expected duration of the project.

b.) Compute the probability that the project will take at least 18 days.

The answer needs to be entered in Excel. Please

Path Activity Time Estimates Top A 4-5-6 B 7-8-10 C 3-5-9 Bottom D 7-8-11 E 2-3-4 F 1-4-6