Question: 3. Network Diagram 3 - Move the boxe development task list. Activity Immediate Predecessor A. Problem Definition - No Predecessor B. Study Current System 1

 3. Network Diagram 3 - Move the boxe development task list.

3. Network Diagram 3 - Move the boxe development task list. Activity Immediate Predecessor A. Problem Definition - No Predecessor B. Study Current System 1 C. Define User Requirements 1 D. Logical System Design 3 E. Physical System Design 2 F. System Development 4, 5 A G. System Testing 6 H. Convert Database 4, 5 1. System Conversion 7, 8/ A D G B E H C F