You own a project management company which has been hired to oversee the construction of a...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
You own a project management company which has been hired to oversee the construction of a new highway in Sydney. The project is currently in the initial construction stages, and about to break ground. There are three separate road segments (1, 2, and 3) which will be built as part of this new highway, and each road segment, there are four jobs (1,2,3, and 4) that need to be completed as part of the site preparation process. The operations of the jobs need to be performed in their natural order (e.g. 1 before 2, 2 before 3, etc.), however not all road segments require all jobs to be performed. Furthermore, there is only one work crew available to complete each job, so the same job cannot be scheduled at the same time on any two road segments. The four jobs required are 1) Site Clearing 2) Tree Removal, 3) Excavation, and 4) Placing Utilities. The time required to complete each job (i.e. processing time) is denoted Pmi, where m is the road segment and i is the job, varies across the road segments. This information is summarized in the table below. Assume the order the road segments will be scheduled is fixed, and equal to 1, 3, 2. Solve the problem and find the optimal makespan (i.e. minimum time required)? Road Segment Required Job Sequence 1,2,3 1 2 3 Answer: 1,2,4 1,2,3,4 Job-Road Processing Times P11-10, P12 8, P13=4 P21-3, P22-8, P24-5 P31-5, P32-4, P33-3, P34-2 You own a project management company which has been hired to oversee the construction of a new highway in Sydney. The project is currently in the initial construction stages, and about to break ground. There are three separate road segments (1, 2, and 3) which will be built as part of this new highway, and each road segment, there are four jobs (1,2,3, and 4) that need to be completed as part of the site preparation process. The operations of the jobs need to be performed in their natural order (e.g. 1 before 2, 2 before 3, etc.), however not all road segments require all jobs to be performed. Furthermore, there is only one work crew available to complete each job, so the same job cannot be scheduled at the same time on any two road segments. The four jobs required are 1) Site Clearing 2) Tree Removal, 3) Excavation, and 4) Placing Utilities. The time required to complete each job (i.e. processing time) is denoted Pmi, where m is the road segment and i is the job, varies across the road segments. This information is summarized in the table below. Assume the order the road segments will be scheduled is fixed, and equal to 1, 3, 2. Solve the problem and find the optimal makespan (i.e. minimum time required)? Road Segment Required Job Sequence 1,2,3 1 2 3 Answer: 1,2,4 1,2,3,4 Job-Road Processing Times P11-10, P12 8, P13=4 P21-3, P22-8, P24-5 P31-5, P32-4, P33-3, P34-2
Expert Answer:
Answer rating: 100% (QA)
From a sample of 1500 adults 48 are males and 52 females About 31 had Dialup connecti... View the full answer
Related Book For
Posted Date:
Students also viewed these general management questions
-
Select indicators from Table 15-2 that would be suitable for finding the end point in Figure 15-3. What color changes would be observed? Figure 15-3 TABLE 15-2 Redox indicators Color Indicator...
-
Select a number base that would be suitable for direct conversion from base 3, and convert the number 22011210 3 to that base.
-
What are electronic payments? How are they different from credit card payments?
-
In a bank reconciliation, deposits in transit are: (a) deducted from the book balance. (b) added to the book balance. (c) added to the bank balance. (d) deducted from the bank balance.
-
Reconsider the unity feedback system discussed in E4.14. This time select K = 120 and K1 = 10. The closed-loop system is depicted in Figure E4.15. (a) Calculate the steady-state error of the...
-
Construct the 5 5 covariance matrix for the 5 data sets in Exercise 8.8.1 and find its principal variances and principal directions. What do you think is the dimension of the subspace the data lies...
-
The polymer matrix material in a linear viscoelastic, unidirectional composite material has a relaxation modulus that can be characterized by the Maxwell model in Figure 8.8. The fibers are assumed...
-
A few years ago, there was a large oil refining company (based in New York) whose top executive was convicted of financial statement fraud. One of the issues in the case involved the way the company...
-
7)A certain city covers an area of 62.294 mil 2 . How many square kilometers is this ?Use the conversion factor 1 mile = 1.61 km 8) A projectile is fired at 422.8 mi/hr. How fast is that in meters...
-
The airline industry defines an on time flight as one that arrives within 15 minutes of its scheduled time. The following table shows the number of on time and late flights leaving Philadelphia and...
-
For a custom to operate as law, it must have SOME characteristics, state FOUR and briefly explain them.
-
A certain metallic structure weighs \(2450 \mathrm{~N}\) on earth. The structure is sent to Mars, which has a diameter of \(6.78 \times 10^{6} \mathrm{~m}\) and mass of \(6.42 \times 10^{23}...
-
Two spherical celestial bodies, one of mass \(3.5 \times 10^{13} \mathrm{~kg}\) and the other of mass \(2.4 \times 10^{18} \mathrm{~kg}\), experience a gravitational force between them with a...
-
A battery and four identical light bulbs are arranged in the circuit of Figure P31.3. Rank the current magnitudes at the nine lettered locations from greatest to smallest. Data from Figure P31.3 90 e...
-
Consider two speres in a system-Sphere 1 has mass \(M\) and radius \(2 R\), while the second Sphere has mass \(2 M\) and radius \(R\). If the two spheres touch each other, find the magnitude of their...
-
(a) How much gravitational potential energy does a system comprising a 150-kg object and the Moon have if the object is one Moon radius above the ground? (b) How far should this object be from the...
-
George and Nancy form EB Corporation with the following investments. George transfers machinery ( basis of $ 1 4 0 k and fair market value of $ 2 0 0 k ) and Nancy transfers land ( basis of $ 1 2 0 k...
-
suppose a nickel-contaminated soil 15 cm deep contained 800 mg/kg Ni, Vegetation was planted to remove the nickel by phytoremediation. The above-ground plant parts average 1% Ni on a dry-weight bas...
-
(a) Follow the steps of Problem 12-11 to solve this one. From the following equilibria, find the concentrations of species and the pH of 1.0 mM La2(SO4)3. Use Davies activity coefficients. You may...
-
To evaluate the equilibrium constant in Equation 6-2, we must express concentrations of solutes in mol/L, gases in bars, and omit solids, liquids, and solvents. Explain why.
-
(a) Considering just acid-base chemistry, not ion pairing and not activity coefficients, use the systematic treatment of equilibrium to find the pH of 1.00 L of solution containing 0.010 0 mol...
-
Describe the relationship between dynamic modeling, behavioral modeling, and structural modeling.
-
Comment on this statement: Dynamic modeling is about interaction.
-
Explain how objects interact by exchanging messages.
Study smarter with the SolutionInn App