Question: 3 Question 2 ( 2 3 pts ) : HealthPlus Inc is producing nebulizers following the process chart given below. Activity times and number of

3
Question 2(23 pts): HealthPlus Inc is producing nebulizers following the process chart given below.
Activity times and number of workers at each activity step are given on the chart. Assume a steady
process and answer the following questions.
a)(8 pts) What is the maximum number of nebulizers that can be produced in an 8-hour workday?
b)(7 pts) If the company would like to produce 480 nebulizers in an 8-hour workday, how many
additional workers we need to hire for each activity? (Assume that company can hire full time
workers only)
c)(8 pts) HealthPlus also manufactures blood pressure monitors. There are two types of monitors:
manual and automatic, and both types are produced using a single dedicated resource pool of 7
workers. (Nebulizer and monitor productions are independent). Chart given below provides
information on monitor production. Calculate the maximum number of monitors that can be produced
in an 8-hour day, given 70 percent of the monitors are manual and the rest is automatic.
Monitor
Processing time
per monitor
Setup time per
batch Batch size
Manual 0.25 hours 2 hours 50
Automatic 0.50 hours 3 hours 75
 3 Question 2(23 pts): HealthPlus Inc is producing nebulizers following the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!