Question: 3. The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item End LCKMG I

3. The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. page 601 a. If 40 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don't need to develop an MRP plan.) b. An order for the end item is scheduled to be shipped at the start of week 8 . What is the latest week that the order can be started and still be ready to ship on time? (Hint. You don't need to develop an MRP plan.) 3. The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. page 601 a. If 40 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don't need to develop an MRP plan.) b. An order for the end item is scheduled to be shipped at the start of week 8 . What is the latest week that the order can be started and still be ready to ship on time? (Hint. You don't need to develop an MRP plan.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
