Question: 3. The table below shows the relevant timing data for a certain project, with durations given in weeks. Draw a Ghantt chart to represent this

3. The table below shows the relevant timing data

3. The table below shows the relevant timing data for a certain project, with durations given in weeks. Draw a Ghantt chart to represent this project information. Note that dependency relationships are deliberately not shown because I want only the Gantt chart, not the network diagram. Do not use MSP! | Activity Duration Start Time End Time A 3 3 4 1 4 5 10 13 10 15 15 16 16 24 10 16 26 26 28