Question: 3. Use the following table: 1 D A Precedence None Duration B 1 5 D B,C 3 Task Form Project Team(b) Interview Users(e) Survey Users

3. Use the following table: 1 D A Precedence None

3. Use the following table: 1 D A Precedence None Duration B 1 5 D B,C 3 Task Form Project Team(b) Interview Users(e) Survey Users Identify New Features Acquire Materials Develop Mkt Camp Prototyping Graphics Design(x) Marketing Survey Customer Sales Calls E 2 F D 4 G D 2. H E 3 1 E 3 F 5 GH,1 3 a). Construct an appropriate AON network showing all values ES, EF, LS, LF, DUR, SL, ID within the node. Legend is required. (10 marks) b) Identify the critical path or paths and the project length