Question: 3. Using the data below, create a time-phased budget for the project. Show how much the daily and cumula- tive costs for the project are,

3. Using the data below, create a time-phased3. Using the data below, create a time-phased

3. Using the data below, create a time-phased budget for the project. Show how much the daily and cumula- tive costs for the project are, just as the monthly and cumulative costs are shown in Exhibit 10.9. Hours per Immediate Predecessor Duration in Weeks Hourly Cost WBS Activity Resource Week 1 Operational definition 1.1 Research literature 3 Becky $35 30 1.2 1.1 1 Ann $60 30 1.3 Identify and define terms Obtain approval of definition Target Selection 1.2 2 Clive $50 20 2 2.1 2 Ann Solicit partners for pilot Hold brainstorming meeting 2.2 2.1 2 Becky 2.3 2.2, 3.1 1 Ann Identify characteristics of targets Obtain approval of partners 2.4 2.3, 1.2, 3.4 1 Clive 3 Question set 3.1 Identify process group members 2 Clive 3.2 Develop question set 2.3 4 Ann 3.3 Prototype and validate question set 3.2 3 Becky 3.4 Add partners 3.1, 2.1 3 Becky Hours per Immediate Predecessor Duration in Weeks Hourly Cost WBS Activity Resource Week 4 Pilot process 4.1 Schedule with target audience 2.4 2 Becky 4.2 Conduct beta test 3.4, 2.4 Clive 2 2 4.3 42 Ann Process feedback from target audience 4.4 Conduct pilot 4.3 2 Clive 4.5 Analyze results 4.4 2 Clive

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!