Question: 3 You manage a project with multiple milestones dependent on each other. One team must hit these milestones before another team can begin their tasks.
3 You manage a project with multiple milestones dependent on each other. One team must hit these milestones before another team can begin their tasks. What type of chart can you use to track this project? 1 point Gantt chart Project status report Roadmap Burndown chart