Question: 30. During, implementation of the software development project, the project manager find an important component was not included in the word breakdown schedule, but it

30. During, implementation of the software
30. During, implementation of the software development project, the project manager find an important component was not included in the word breakdown schedule, but it is 10% over budget. To include the component in the revised WBS, which step should the project manager implement? A Report the situation to the sponsor B. Immediately modify the WBS, add the missed component in it C Do not make change, it will cause over budget D. Initiating change requests and assess the impact of various aspects with the team