Question: 32. ( 30 points) For a given activity, Optimistic time =17 days, Most likely time =29 days and Pessimistic time =47 day Calculate: a. Weighted

32. ( 30 points) For a given activity, Optimistic
32. ( 30 points) For a given activity, Optimistic time =17 days, Most likely time =29 days and Pessimistic time =47 day Calculate: a. Weighted average activity time and variance b. From the above calculation, use the weighted average time and vari: calculate 1. Probability of completing the project greater than 25 days 2. Probability of completing the project less than greater tha days 3. Probability of completing the project between 25 and 30