Question: 3.2.1 Determine the total completion time and the critical path for the project. 3.2.2 Determine the Early Start, Early Finish, Late Start, Late Finish, and

3.2.1 Determine the total completion time and the critical path for the project.
3.2.2 Determine the Early Start, Early Finish, Late Start, Late Finish, and Slack for each activity
EPT2602 STUDY GUIDE (1) X Principles of Operations MX G What is the advantage of: x + Els/101_2021_3_b.pdf 14 / 22 10096 + 3.1.2 Determine the project critical path and the expected project completion 3.1.3 What is the probability that the project will be completed in less than 45 3.2 Consider the activities below for the construction of an old age home. Activity Immediate Predecessor Activity Duration (Days) 7 A B 2 15 D E 8. E A.B. 10 F D 2 G ED 5 H G 8 1 C F 2. J 3 DI281S ALLESStep by Step Solution