Question: 324 Chapter 9 Reducing Project Duration Use the information contained below to compress one time unit per move using t least cost method. Reduce the
324 Chapter 9 Reducing Project Duration Use the information contained below to compress one time unit per move using t least cost method. Reduce the schedule until you reach the crash point of the netw For each move identify what activity (ies) was crashed and the adjusted total cost Exercises te: The correct normal project duration, critical path, and total direct cost a vided Crash Cost (Slope) Normal Time Normal Cost 150 100 Act. Maximum Crash Time 100 60 70 150 project duration:12 Total direct cost: 1000