Question: 32.True or False: To set the baseline, from Project: Schedule click the Set Baseline icon and choose Set Baseline. Ensure that both the default Set
32.True or False: To set the baseline, from Project: Schedule click the Set Baseline icon and choose Set Baseline. Ensure that both the default Set Baseline button and the default Entire project options are selected and click OK.
33. True or false: Microsoft Project considers a resource overallocated if that resource is assigned to more than 8 hours of work on any given day in the project (assuming 100% maximum units and 8 hours per working day).