Question: 3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed

3.8

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

ACTIVITY

IMMEDIATE PREDECESSOR(S)

TIME (DAYS)

A

-

2

B

-

5

C

-

1

D

B

10

E

A, D

3

F

C

6

G

E, F

8

a) Develop an AON network for this problem.

b) What is the critical path?

c) What is the total project completion time?

d) What is the slack time for each individual activity?

4.6

The monthly sales for Yazici Batteries, Inc., were as follows:

MONTH

SALES

January

20

February

21

March

15

April

14

May

13

June

16

July

17

August

18

September

20

October

20

November

21

December

23

a) Plot the monthly sales data.

b) Forecast January sales using each of the following:

i) Naive method.

ii) A 3-month moving average.

iii) A 6-month weighted average using .1, .1, .1, .2, .2, and .3, with the heaviest weights applied to the most recent months.

iv) Exponential smoothing using an a = .3 and a September forecast of 18.

v) A trend projection.

c) With the data given, which method would allow you to forecast next Marchs sales?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!