Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
.png)
a) Draw the appropriate AON PERT diagram for J.C. Howard's management team.
b) Find the critical path.
c) What is the project completion time?
IMMEDIATE ACTIVITY PREDECESSOR(S) TIME (DAYS) 10 A, D E, F
Step by Step Solution
3.42 Rating (171 Votes )
There are 3 Steps involved in it
a b Critical path is BDEG c Total project takes 26 days Activity ... View full answer
Get step-by-step solutions from verified subject matter experts