Question: 3rd Case Study (40 points) Create a diagram with the following activities on arrow in order to satisfy the relations bellow: Activities A, B and

3rd Case Study (40 points) Create a diagram with

3rd Case Study (40 points) Create a diagram with the following activities on arrow in order to satisfy the relations bellow: Activities A, B and C are the first activities of the project and they can start immediately A, B precedes D B precedes D, E, F and H F and C precedes activity G E and H precedes activities and J Activities C, D, F and I precedes activity K K precedes activity L Activities I, G and L are the last activities of the project. . Assign numbers to nodes and you have to define three dummy activities