Question: 4 1 . 1 % complete Question During final inspection of a deliverable, the quality team observes that there is a deviation on a particular

41.1% complete
Question
During final inspection of a deliverable, the quality team observes that there is a deviation on a particular component. The customer, however, has not indicated anything with regard to this in its specifications.
What should the project manager do?
A.Raise the matter to a technical expert.
B.Conduct a quality assurance audit.
C.Approve the deliverable as it does not deviate from any customer specifications.
D.Reject the deliverable, citing deviation from the project specifications.