Question: 4. (10 Points) Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of July 6, 2020.

4. (10 Points) Create a Gantt Chart for the

4. (10 Points) Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of July 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will the project be completed? Activity Task Duration (Days) Task Number Immediate Precedence 1. Strategic Planning Phase none 20 2. Team Orientation 1 5 3. Software Configuration 2 16 4. Testing 3 20 5. Training 2 10 6. Facility Modification 40