Question: 4 (1.50 points) A project by Thomas Weber has an expected duration of 40 weeks and a variance of 25 weeks2. The project duration is
4 (1.50 points) A project by Thomas Weber has an expected duration of 40 weeks and a variance of 25 weeks2. The project duration is assumed to be normally distributed. a) What is the probabil