Question: 4) 4) Given the critical path below (A -B-C), calculate the following a. The crash cost per unit time savings for each activity. [10 points]

4) 4) Given the critical path below (A -B-C),
4) 4) Given the critical path below (A -B-C), calculate the following a. The crash cost per unit time savings for each activity. [10 points] b. The maximum total crash time savings and cost. [10 points) c. The maximum total time-savings with a $6000 budget. [10 points] Crash Duration Activity Normal Time Normal Cost Crash Cost A 8 days $8,000 5 days $11,000 B 5 days $2,000 2 days $9,500 10 days $9,000 8 days $12,000