Question: 4 B Using the network and table below, find: D 2 Crash 4 Crashed Normal A 5 Time Cost Time Normal Activity (days) (total) (days)

4 B Using the network and table below, find: D 2

4 B Using the network and table below, find: D 2 Crash 4 Crashed Normal A 5 Time Cost Time Normal Activity (days) (total) (days) Cost A 3 $500 4 $300 B 325 250 3 4 550 7 400 (3 D 3 250 5 150 a) (4 pts) The crash cost per day b) (6 pts) Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing is allowed. 1 3