Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

4. Based on precedence diagram given below, use the longest task time heuristic to balance the line. Cycle time = 1.3 minute Task and time

4. Based on precedence diagram given below, use the longest task time heuristic to balance the line. Cycle time = 1.3 minute

Task and time (min.)

A, 0.2

B, 0.4

C, 0.3

D, 1.3

E, 0.1

F, 0.8

G, 0.3

H, 1.2

A)What is the balance delay?

B)Out of all workers placed which worker is the happiest (has most remaining time)?

PLEASE USE THE GRAPH BELOW TO ANSWER THE QUESTION

Work Station

Eligible

Assigned Task

Assigned Time

Remaining Time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Line Balancing using Longest Task Time Heuristic Cycle Time 13 min Work Station Eligible Assigned Ta... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations And Supply Chain Management

Authors: F. Robert Jacobs, Richard Chase

14th Edition

978-0077824921, 78024021, 9780077823344, 007782492X, 77823346, 978-0078024023

More Books

Students also viewed these General Management questions