Question: 4. Based on precedence diagram given below, use the longest task time heuristic to balance the line. Cycle time = 1.3 minute Task and time

4. Based on precedence diagram given below, use the longest task time heuristic to balance the line. Cycle time = 1.3 minute

Task and time (min.)

A, 0.2

B, 0.4

C, 0.3

D, 1.3

E, 0.1

F, 0.8

G, 0.3

H, 1.2

A)What is the balance delay?

B)Out of all workers placed which worker is the happiest (has most remaining time)?

PLEASE USE THE GRAPH BELOW TO ANSWER THE QUESTION

Work Station

Eligible

Assigned Task

Assigned Time

Remaining Time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Line Balancing using Longest Task Time Heuristic Cycle Time 13 min Work Station Eligible Assigned Ta... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!