Question: which worker is the happiest with most remaining time? Out of all workers placed which worker is the happiest (has most remaining time)? 4. Based

Out of all workers placed which worker is the happiest (has most remaining time)? 4. Based on precedence diagram given below, use the longest task time heuristic to balance the line. Cycle time =1.3 minute Total task time: 0.2+0.4+0.3+1.3+0.1+0.8+0.3+18=4.6 Total station rime: 41.3=5.2 4.65.2=0.884615100=88.5 utilizatwh: What is the balance delay? 10088.5=11.5%