Question: 4. Consider the following project tasks. E 5 Activity | A | B | C D Duration 1 2 3 4 Predecessor - - -

4. Consider the following project tasks. E 5

4. Consider the following project tasks. E 5 Activity | A | B | C D Duration 1 2 3 4 Predecessor - - - A A. Draw the project's network. (1 pt.) F G 4 6 B C H 6 D E I 2 G J 3 H, F, I B B. Identify the project's critical path. (1 pt.) C. Calculate the slack (float) of all activities. (1 pt.) Activity Slack Series A B CDBF0 A B C D E F G H