Question: 4). Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal condition are as follows: Activity Duration in Weeks Crew
4). Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal condition are as follows:
| Activity | Duration in Weeks | Crew size |
| AC | 6 | 8 |
| BC | 6 | 7 |
| BE | 2 | 6 |
| CD | 3 | 2 |
| CE | 4 | 1 |
| DF | 7 | 4 |
| EF | 4 | 6 |
| FG | 5 | 10
|
- Extra crew members can be used to expedite activities BC, CE, DF, and EF at a cost given below:
| Extra Crew | Weeks Saved | Crash cost per week |
| 1 | 1 | $100 |
| 2 | 2 | $120 |
| 3 | 2 | $200 |
| 4 | 3 | $250 |
If there is a penalty cost of $1,250 per week beyond the minimum maintenance time of 20 weeks, recommend the minimum cost schedule.
- (Independent of part c) The table below, based on historical completion times, gives three estimates for each activity completion time. Determine the mean and variance of the expected project completion time and calculate the probability that the project is completed within the 20-week minimum maintenance time.
| Activity | Optimistic | Most Likely | Pessimistic |
| AC | 5 | 6 | 8 |
| BC | 4 | 6 | 10 |
| BE | 2 | 2 | 2 |
| CD | 2 | 3 | 7 |
| CE | 2 | 4 | 9 |
| DF | 5 | 7 | 13 |
| EF | 3 | 4 | 6 |
| FG | 4 | 5 | 16 |