Question: Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal conditions are as follows: Activity Duration (weeks) Crew size AC

Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal conditions are as follows: Activity Duration (weeks) Crew size AC 4 6 BC 6 8 BE 3 3 CD 2 3 CE 4 2 DF 6 4 EF 5 5 FG 4 8 i) Represent the maintenance project in the form of an activity-event network. ii) Identify the critical path and find the minimum time for project completion. iii) Extra crew members can be used to expedite activities BC, DF and EF at a cost given below: Extra crew Weeks saved Crash cost per week 1 1 $100 2 2 $125 3 2 $150 4 3 $200 If there is a penalty cost of $1,200 per week beyond the minimum maintenance time of 16 weeks, then recommend the minimum-cost schedule.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!