Question: 4. Given the data and information that follow, compute the total direct cost for project duration. If the indirect costs for each project duration are

4. Given the data and information that follow, compute the total direct cost for project duration. If the indirect costs for each project duration are $90 (15 units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project for each duration. What is the optimum cost-time schedule for the project? W is this cost? Act. Crash Cost (slope) Maximum Crash Time Normal Time Normal Cost 30 50 60 60 0 70 10 50 60 100 100 90 30 50 200 200 $730 C Initial 4 2 project duration 15 G 2 5 Total direct cost $730 B 2 ct Management the Managerial Process, McGraw-Hill US Higher Ed ISE, 2020, ProQuest Ebook Central letall.action?docID=6148222