Question: 4. Given the following data, perform a critical path analysis in Excel to determine the projects critical path. Your spreadsheet should indicate the early start


4. Given the following data, perform a critical path analysis in Excel to determine the project’s critical path. Your spreadsheet should indicate the early start schedule, late start schedule, and slack.



Draw a network diagram for the project described in question 4.

Draw a network diagram for the project described in question 4.


Activity Duration Predecessors A 3 weeks B 15 weeks A C 5



Using the provided data values for minimum expected activity durations and maximum expected activity durations, use Excel to provide a PERT analysis of the project given in question 4. Include all calculations and formulas.


weeks D 3 weeks E 6 weeks F 4 weeks E G

Activity Duration Predecessors A 3 weeks B 15 weeks A C 5 weeks D 3 weeks E 6 weeks F 4 weeks E G 2 weeks D, F

Step by Step Solution

3.47 Rating (150 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!