Question: 4. Is this graph an Euler circuit?? Why/Why Not? D , E B F 5. Find the critical path, Finish Time, Early Start & Early

4. Is this graph an Euler circuit?? Why/Why Not?

4. Is this graph an Euler circuit?? Why/Why Not? D , E B F 5. Find the critical path, Finish Time, Early Start & Early Finish, Late Start & Late Finish, and slack time for all tasks of the following project given this information. A-3, B-4, C-3, D-2, E-4, F-6, G-5, H-5, 1-6, J-2, K-8, L-5 D-2 START E-4 F-6 G-5 FINISH A-3 B-4 L-5 H-5 K-8 J-2 PERT 6. Given a most likely time of 6 hours, a pessimistic time of 10 hours and an optimistic time of 3 hours find the PERT task duration for this information