Question: Activity Predecessor Duration A - 6 B A 1 1 C A 7 D B , C 3 E D 2 Critical Path: Calculate the

Activity Predecessor Duration
A -6
B A 11
C A 7
D B,C 3
E D 2
Critical Path: Calculate the early start, early finish, late start and late finish dates for all activities by performing a forward and backward pass analysis through the schedule network. The convention for the project starts on day 0. What is the total float for Activity D?
a.
0
b.
2
c.
5
d.
1