Question: Activity Predecessor Duration A - 6 B A 1 1 C A 7 D B , C 3 E D 2 Critical Path: Calculate the
Activity Predecessor Duration
A
B A
C A
D BC
E D
Critical Path: Calculate the early start, early finish, late start and late finish dates for all activities by performing a forward and backward pass analysis through the schedule network. The convention for the project starts on day What is the total float for Activity D