Question: 4. It is important to assign a unique name and a unique number to every component in the project Work Breakdown Structure. a. True b.

4.

It is important to assign a unique name and a unique number to every component in the project Work Breakdown Structure.

a. True
b. False

5.

In order to plan for a project meeting, project managers should develop an agenda. Which of the statements below is NOT accurate with respect to a project meeting agenda?

a. the agenda should state the purpose of the meeting.
b. the agenda should list the major topics of the meeting in the order in which they will be covered.
c. the agenda should only be shared with senior management.
d. the project manager should assure the agenda is prepared and distributed ahead of time.

6.

________ is the process of the project team communicating and working with stakeholders to satisfy their needs (and additional desires, when possible), handle issues quickly and encourage active stakeholder participation throughout.

a. Manage Stakeholder Engagement
b. Identify Stakeholders
c. Plan Stakeholder Engagement
d. Analyze Stakeholders

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!