Question: 4. Lead time for a certain part is 2 weeks, and the order quantity is 50 . By completing this MRP record below, answer the
Lead time for a certain part is 2 weeks, and the order quantity is 50 . By completing this MRP record below, answer the following question: What are the Net requirements of the part in Week 3 ? What action shpuld be taken? 50 30 0 25 None of the above