Question: 6. Lead time for a certain part is 2 weeks, and the order quantity is 50 . By completing this MRP record below, answer the
Lead time for a certain part is 2 weeks, and the order quantity is 50 . By completing this MRP record below, answer the following question: What action should be taken in Week 1 an order for 50 should be released in week 1. an order for 100 should be released in week 1. no order should be released in week 1 None of the above