Question: Lead time for a certain part is 2 weeks, and the order quantity is 50 . By completing this MRP record below, answer the following


Lead time for a certain part is 2 weeks, and the order quantity is 50 . By completing this MRP record below, answer the following question: What are the Net requirements of the part in Week 3 ? What action should be taken? 50 30 5 25 20 Lead time for a certain part is 2 weeks, and the order quantity is 50 . By completing this MRP record below, answer the following question: What is the Projected Available Inventory of the part in Week 3 ? 50 30 5 25 None of the above