Question: ( 4 points ) The advantage ( s ) of a traditional project delivery method is ( are ) : a . Reduced project time
points The advantages of a traditional project delivery method is are:
a Reduced project time
b No adversarial relationships among participants
c Shared risks and rewards among key players
d Known project cost before construction
e All of the above
points Which of the following statements is NOT correct?
a It is acceptable to use a single node to represent multiple activities.
b A forward pass is used to determine the early start and early finish times.
c Certain key events are called milestones.
d The longest sequence of activities required to complete the project is known as the critical path.
e Bar chart schedules are less effective than network schedules in depicting relationships between activities.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock