Question: ( 4 points ) The precedence diagram network for a project is shown below, along with the optimistic ( T o ) , most likely
points The precedence diagram network for a project is shown below, along with the optimistic most likely and pessimistic durations for each activity. Use the PERT process to determine the probability in percent of completing the project in days or less.
points After construction of the formwork for precast concrete girders started, the durations to construct the formwork for the first two girders on the project were as follows:
Girder : hours
Girder : hours
Using an improvement rate based on individual units, answer the following questions:
a What is the rate of improvement
b How long in hours will it take construct the formwork for the girder?
c In an attempt to accelerate the schedule, the contractor plans to ask the formwork crew to work hours per day for days a week. What will be the time required hours to construct the formwork for the girder with the impact of overtime included?
points Based on data from prior projects, the cumulative average time to design the formwork for precast concrete girders is hours per girder with an engineer's rate of learning of when designing formwork. Assume no impacts of working overtime.
a What will be the average time per girder that is required to design the formwork for all girders?
b What will be the total time required to design the formwork for all girders?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock