Question: 4: Project ABC is planned for 15 months with a budget (BAC) of $150,000. If the scheduled percentage of work completed after three months is

4: Project ABC is planned for 15 months with a budget (BAC) of $150,000. If the scheduled percentage of work completed after three months is 20%, What is the PV after three months? Your answer here (show your work)