Question: 4. Table 2 shows the cost data status at the end of the fourth month: Table 2: Project Z, Task 3 Cost Data Status At

4. Table 2 shows the cost data status at the end

4. Table 2 shows the cost data status at the end of the fourth month: Table 2: Project Z, Task 3 Cost Data Status At End of Fourth Month (Cost in Thousands) SUBTASKS STATUS BCWS BCWP ACWP 1 Completed 100 100 100 2 Completed 50 50 55 3 Completed 50 50 40 Not Started 0 5 Completed 90 90 Not Started 40 0 0 7 Started 50 50 25 Not Started 4 70 0 140 6 8 TOTAL (a) (b) Determine the progress and cost status for EACH of the subtasks Where BAC is the value of BCWS at completion = RM579.000, estimate the cost at completion for Task 3 (25 marks)