Question: 4. The activities for a sub-project within a unit development project are shown in the table below. The project is restricted in funds after day
4. The activities for a sub-project within a unit development project are shown in the table below. The project is restricted in funds after day 14 , since only9000per day can be released. i) As sub-project manager you have1000of reserve funds, can the sub project be completed on time and despite the restrictions imposed? Show your answers by drawing a Gantt chart and resource histograms before and after any actions that you take to resolve the situation