Question: The activities for a sub-project within a unit development project are shown in the table below. Activity Predecessor Duration (days) Funds Required (per day) A
The activities for a sub-project within a unit development project are shown in the table below. Activity Predecessor Duration (days) Funds Required (per day) A 3 3000 B A 9 4000 C A 7 5000 D B 5 5000 E B 4 4000 F C 3 3000 G D 4 2000 H A, E 3 3000 J F 7 4000 K G,H, J 4 6000 The project is restricted in funds after day 14, since only 9000 per day can be released.
i) As sub-project manager you have 1000 of reserve funds, can the sub project be completed on time and despite the restrictions imposed? Show your answers by drawing a Gantt chart and resource histograms before and after any actions that you take to resolve the situation